Home Remodeling Tips - The Construction Phase

Should I move out?position. A qualified contractor should have sufficient
The first important thing to consider is will remain inresources to fund the construction of the job
your home or move out for the duration of thewithout advances.
project. If your project involves any substantialThe frequency of progress payment should be
remodeling of existing spaces, I urge you to move todefined in the contract usually weekly, bi-weekly or
temporary quarters. What do I mean by substantial?monthly. When the contractor submits his application
Well if it is anything more than painting or floorfor payment, the site should be visited and the
coverings, the work is substantial. Work that involvesapplication verified against the actual work performed.
moving walls, reworking electrical, plumbing orHere is another instance when having an architect on
mechanical systems can make your home unlivable.your team pays many times over. An architect will
Rent the movie “The Money Pit” andvisit the site, verify the work in place and provide
see what I mean. On the other hand, if you areyou with a written report. He will also certify the
having an addition to your home, you may be able toapplication for payment.
remain and not be overly affected by the work. YouWith this paperwork in hand you can feel confident
should discuss your options with your architectthe contractor is not being paid for work in advance.
designer early on in the project.On a personal note, the very first job I monitored
If you are going to vacate, then move all yourearly in my career the contractor submitted a
belongings out of the areas of work to a securepayment application with a huge advance he said was
location. With the contractor in full control of yourfor materials he had ordered. I refused to certify the
property, you don’t want things to disappear.payment. We later found out he was trying to
You also may realize some savings since thescrape together enough money to pay for his
contractor will know his workflow will beColorado deer hunting trip the next week!
uninterrupted.Retainage
PermitsRetainage is another issue to be considered during
A building permit is generally required wheneverthe contract negotiations and is an important
structural work is involved or when the basic livingsafeguard for you as owner. I recommend 10% be
area of a home is to be changed. To be sure, checkwithheld from every payment application. Your
your local requirements. If your contract does notarchitect can advise you on this. The purpose of
provide that the contractor will obtain the permitsretainage is simply to keep the contractor interested
and he doesn't, you may be held legally responsible.in finishing the project. There is an old saying in
Do not get any permit yourself. If you do, you will beconstruction that “the last 5% of a job is the
considered to be the contractor, and you could behardest to complete”. By the time your
held liable if the work does not comply with theproject is 95% complete, the contractor has likely
building codes.started another job. His attention is naturally focused
Notice to Proceedon the job that will make him the most money for
Prior to starting work, you should issue a formalthat current month. Having an extra 10% keeps him
"Notice to Proceed". This will serve to document theinterested in completing your job.
official start date for the project and will define theThe final payment including retainage is normally not
agreed completion date. This is important for severalapproved until all work has been inspected, all
reasons. First the dates of start and completion arepaperwork is turned in and any requirements of local
clearly spelled out. Second, many states have timebuilding officials have been completed.
limitations on when Liens can be filed based on thoseProtect yourself
dates. Third, it lets the contractor know you will beOnce the work begins, if your contractor will have to
monitoring his progress. You don’t want touse subcontractors, you should protect yourself from
have to be asking the contractor when he will beliens against your home in the event the primary
done and his answer every time is "two weeks".contractor doesn't pay the subcontractors or
Schedule of Valuessuppliers. You can do this by insisting upon a lien
Most standard construction contracts require therelease from all subcontractors and suppliers before
contractor to furnish you with a Schedule of Values.you pay for any work. Or, you can use the services
The Schedule of Values is a detailed statementof a construction control company. For a small
furnished by the contractor, builder or others outliningpercentage of your contract price, you may deposit
the portions of the contract sum. It allocates valuesyour payments with them and they will disburse the
for the various parts of the work and is also used asfunds and secure the lien releases for you. Although
the basis for submitting and reviewing progressthey are not required to inspect the work, they
payments.generally do.
The schedule will be broken down by the majorInspections
steps in the project making it easy to monitor theInspections will occur throughout the project. There
progress of the job as well as validate applicationswill be local required inspections performed by the
for payment. For example, the schedule of valueslocal building officials. Additional inspections will be
allows $2000 for interior doors. The contractorperformed to certify payment applications and to
submits a payment application that includes $2000 formonitor the progress of the work.
interior doors. If the inspection shows all the interiorChange Orders
doors are in place, the contractor is entitled to fullEven with the best plans and specifications,
payment for the interior doors. If the inspectionsometimes hidden conditions will be uncovered that
shows half the interior doors are in place, thewill require a change order. These conditions can
contractor is only entitled to 50% or $1000 on therange from problems with the soils on your site to
current payment application.uncovered substandard construction that must be
Monitor progress dailybrought into compliance with current codes. For too
During the course of the work, it is important youmany contractors, this is where they plan to make
visit the work area on a daily basis. The best time istheir money by bidding low to get the job and then
after working hours. This way you can see if thehitting you with a flurry of inflated change orders.
contractor is proceeding in a timely manner. This dailyYour architect will assist you in validating any change
monitoring can alert you early on to potentialorders negotiating a true and fair cost.
problems the contractor may have being able to manAlso be aware, if you decide to make changes during
the job or pay for materials.the course of the work because you don’t like
Take photossomething or want a different material, you will
There is no better way to document progress andreceive a change order and the price will be much
problems than by taking photos and lots of them. Ihigher than if you made the change during the
suggest you buy a digital camera if you don’tplanning stage. Again, proper planning will eliminate or
have one and use it every time you visit the site.minimize these costly change orders. It is not unusual
Paymentsfor a poorly planned project to double in price during
First, on the subject of down payments, my adviceconstruction.
to you is making a down payment weakens your